Redcar and Cleveland Council has programmed its annual four-week period of principal road maintenance across the Borough, with work involving gully and sign cleaning, grass cutting plus repairs to street lights and carriageways.
The work, which will be timed from 9am-3pm to avoid early morning and homeward bound traffic, starts on Monday, April 28, with a six-day schedule on the A171 from Swans Corner to Middlesbrough Road, South Bank, finishing on Tuesday, May 6.
The second phase, from Wednesday, May 7 to Tuesday, May 13, will tackle the A1053 Trunk Road and the A66 from the Wilton International site's West Gate roundabout to Cargo Fleet Lane roundabout.
The third phase, from Wednesday, May 14 to Friday, May 16, covers the A1085 Trunk Road, from the West Coatham Lane roundabout to Corus Lackenby. At the same time, Thursday, May 15 and Friday, May 16, work will be carried out on the A171 Birk Brow.
The final work schedule is on the A174 from Greystones roundabout to the Redcar Lane roundabout from Monday, May 19 to Thursday, May 22.